COMMERCIAL PROJECTS

Nearing completion of a complete overhaul to the roof, dock levellers, bay doors and bumpers plus extensive external redecoration work.
Warehouse and external lighting replaced with LED and the out of service passenger lift was refurbished. 

DHL SPITFIRE ROAD

01

press to zoom

press to zoom

press to zoom

press to zoom
1/4

press to zoom

press to zoom

press to zoom

press to zoom
1/3

02

DHL CANNOCK

On behalf of DHL, Flexispace carried out some works to Cannock which mainly consisted of roof works. These included removal of vegetation, replacement of tubular lighting, supplying and fitting ceiling tiles, to mention a few.

press to zoom

press to zoom

press to zoom

press to zoom
1/4

03

DHL MAIDSTONE

Over 2018 and 2019 we had a 12 month contract with DHL to be a constant presence on site at DHL Maidstone. Carrying out refurbishments on WC's & locker rooms, canteen creating a "chill zone" upgrading lighting and carrying out electrical testing, emergency repairs and maintenance to loading bays, as well as decorating offices. 

press to zoom

press to zoom

press to zoom

press to zoom
1/3

04

DHL LUTTERWORTH

The first stage is to take the tracking system down

Flexispace were awarded the contract for Large Mez, Small Mez, Enviro Office and Dexion Racking Removal.

Large Mez:

Electrical ,data, fire alarm, access/cctv and mechanical strip out, strip and remove mez, flooring and make good of bolts.  

Small Mez 

Electrical ,data, fire alarm, access/cctv and mechanical strip out, strip and remove mez, flooring and make good of bolts, drain down and cap-off redundant sprinkler pipework

Enviro Office

  • Removal of sprinkler system

  • Removal of data, CCTV and fire alarm installations

  • Removal of input/extract fans and associated ductwork and grills

  • Patch up external cladding

  • Removal of the partitions, ceilings and floor coverings

Dexion Racking Removal

  • Dismantle all parts by hand and palletise